How to Specify a Server Power Inductor for a Multiphase Buck Converter
Use per-phase peak and RMS current to specify a server power inductor. Account for current sharing, winding ripple, phase shedding and thermal limits.
For a server power inductor in a multiphase buck converter, use the worst-case peak current in the winding to check inductance under bias. Use the winding RMS current and switching ripple to assess heating. Total rail current describes the load and helps establish the average current per active phase.

Example of a board-level voltage regulator with visible inductors. Photo by Dsimic (resized and padded) via Wikimedia Commons, CC BY-SA 4.0.
How much current flows in each phase?
In a balanced four-phase converter supplying 80 A, the nominal average is 20 A per phase. With symmetrical triangular ripple of 8 A peak-to-peak per phase, the nominal peak is 24 A and the RMS current is about 20.1 A. These numbers are a worked example. Allow for sharing error, changing active phase count and load transients before setting a real current limit.
| Quantity | Where to evaluate it | How it informs the specification |
|---|---|---|
| Rail output current | At the combined load | Sets total output demand and, with the active phase count, the nominal current share. |
| Per-phase average and peak current | In each winding | Peak includes the upper excursion of the ripple. Check retained inductance at the highest relevant bias and temperature. |
| Per-phase RMS current and ripple | In the same winding, over a stated time window | Use the waveform and switching frequency to estimate winding loss and verify temperature rise. |
| Combined output ripple | After the phase currents sum | Helps assess output filtering. Cancellation depends on phase timing and duty cycle. |

Illustrative balanced two-phase example. The plots have independent vertical offsets and show no measured data. Original illustration by LFDJ.
Which operating cases belong on the brief?
Include full load, relevant phase-shedding states and a load step if that transient drives peak current. Record the active phase count, rail voltages, switching frequency, current waveform and actual airflow or cooling. For coupled windings, identify the coupling arrangement and ask for the relevant winding and transient inductance definitions.
What should the inductor enquiry include?
State the minimum inductance at the required bias and temperature, continuous and peak currents per winding, allowable ripple, and height and footprint limits. Attach a labelled stage diagram and waveform when available.
Data center power magnetics · Compare power inductor data sheets · Browse power inductors · Send a product enquiry
Technical references Texas Instruments, Benefits of a Multiphase Buck Converter